Close Menu

    Subscribe to Updates

    Get the latest creative news from FooBar about art, design and business.

    What's Hot

    How to Perfectly Illuminate Every Room in Your Home

    May 15, 2025

    Blocked Drains in the Eastern Suburbs – Fast & Professional Drain Clearing

    May 13, 2025

    Looking for Reliable Electricians in Cranbourne? Here’s Why Locals Trust Southside Electrics

    May 13, 2025
    Facebook X (Twitter) Instagram
    Business Vibrant
    • Home
    • Business
    • Tech
    • Real Estate
    • Celebrity
    • About Us
    • Contact Us
    Business Vibrant
    Home » Blog » CPM PRINCIPLES AND THE METHODOLOGIES
    Business

    CPM PRINCIPLES AND THE METHODOLOGIES

    EllianaBy EllianaNovember 1, 2024No Comments5 Mins Read16 Views
    Facebook Twitter Pinterest LinkedIn Tumblr Email
    Share
    Facebook Twitter LinkedIn Pinterest WhatsApp Email

    Table of Contents

    • Critical Path Method 
      • The Principles of Critical Path Method 
      • Activity
      • Dependency 
      • Sequence
      • Activity Duration
    • Critical Path
      • Total Float/ Total Slack
      • Methodologies of Critical Path Method
      • Network Diagram
      • Logic of the CPM network
      • Longest Path
      • Calculation of Total Float/ Total Slack
    • Summary

    Critical Path Method 

    The Critical Path Method (CPM) is one of the Activity-On-Arrow (AOA) project management network procedures applied in project management to establish the sequence of the longest path and shortest duration for project finish.

    The Principles of Critical Path Method 

    The principles of the Critical Path Method (CPM) are described below.

    Activity

    An activity in a project schedule is defined as a unique task with a start date, finish date, and duration. A project is split into activities at the lowest Work Breakdown Structure (WBS) level. The activities consume duration and resources within a project. In the CPM network diagram, a project’s activities are shown by arrows pointing in the progressing direction.

    Dependency 

    Dependency is the affiliation between activities that are linked with each other with predecessors and successors.  The start or finish of an activity depends on the progress of the predecessor activity.

    Sequence

    The sequence is the logical arrangement of the planned performance of activities. The sequence of activities is illustrated by arrows in a CPM network diagram. 

    Activity Duration

    Activity duration is the time needed to complete an activity. This can be estimated using data from the completed projects that are of similar type, PERT, or other techniques.

    Critical Path

    The critical path is the longest in a project schedule. The activities in the critical path are termed critical activities.  If there is any delay in critical activities, it will adversely impact the project finish date.     

    Total Float/ Total Slack

    Total float/ total slack is the time by which an activity can be delayed without delaying the successor activity and the project finish date. The critical activities in the longest path have zero total float/ total slack and any delay in these activities will delay the project’s  completion. The non-critical activities in the CPM network have a total float/ total slack of more than 0 days. The positive total float available for the non-critical activities provides flexibility and with any delay less than the available total float will not delay the project completion.

    Methodologies of Critical Path Method

    The methodologies for Critical Path Method (CPM), Network Diagram critical path, and computation of total float/ slack for the activities are explained below.

    Network Diagram

    A Network Diagram in CPM is a graphical representation of tasks, dependencies, and the order for the occurrence of planned tasks in a project schedule. CPM scheduling consultants often rely on these diagrams to illustrate the sequence and dependencies of activities in a project. The activities and the order of occurrence are illustrated using arrows in the network diagram. The start and finish of each event/node are joined as per the logic by an arrow. In addition, dummy activities are introduced to maintain the logic of the sequence of activities.

    For instance, we will consider a simple CPM network for easy understanding, as shown in Figure 1 below. The network consists of 6 activities named: A, B, C, D, E, and F. The duration of the previously mentioned activities is 2, 3, 2, 1, 3, and 2 days, respectively.         

    Figure 1: CPM Network Diagram

    Logic of the CPM network

    The logic of the CPM network illustrated above is as follows.

    • Activity A, B, and C are independent activities and start at the same time.

    • Activity D starts after activities A, and B are finished.

    • Activity E starts after activities C and D are finished.

    • Activity F starts Activity after activity C is finished.

    • Activities E and F are to be completed before the project finishes.

    The points to be noted in the above-mentioned CPM network diagram are as follows.

    • Activities A and B are concurrent as shown in the network diagram.

    • The dummy activities are shown as dotted lines in the above CPM network.

    • The dummy activity G is used to provide a logical relationship between Activity B and D. (Activity B is to be completed before the start of Activity D)

    • The dummy activity H is introduced to illustrate the logical relationship between Activities C and E.

    Longest Path

    The longest path of the above CPM network and total project duration shall be determined as follows. There are 4 possible paths based on the logical sequence of the above CPM network which are tabulated below.

    Sl. No Activity path  Calculated duration Remarks
    1 A, D, E 2 days + 1 days + 3 days = 6 days  
    2 B, D, E 3 days + 1 day + 3 days = 7 days Longest Path
    3 C, E 2 days + 3 days              = 5 days  
    4 C, F 2 days + 2 days              = 4 days  

    Table 1:  Calculation of the longest path

    The longest path of the network runs through activities B, D, and E and the total project duration is 7 days. The critical activities in the network are Activity B, D, and E which are in the longest path of the network.

    Calculation of Total Float/ Total Slack

    The total float/total slack for the activities in the above CPM network shall be calculated as follows.

    Activity Total float/ Total slack Remarks
    A 1 day (Duration of B- Duration of A).  Non-critical activity
    B 0 day  Critical activity
    C 2 days (Duration of B + Duration of D)- Duration of C, non-critical activity
    D 0 days Critical activity
    E 0 days Critical activity
    F 3 days (Duration of the longest path)- (Duration of C+ Duration of F), Non-critical activity

    Table 2:  Calculation of total float/total slack

    Summary

    The critical path method is useful for developing a realistic project schedule with a logical sequence of activities. Critical and non-critical activities shall be observed using this technique which will be helpful for effective resource management, and time management, and to ensure the project is completed on time and within the budget.

     

    Elliana
    Elliana
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Previous ArticleMaking the Most of Probationary Periods in Employment
    Next Article How Cash Buyers Offer Solutions for Homeowners Facing Foreclosure in Tampa
    Elliana
    • Website
    • Facebook

    Related Posts

    Patrick Auto Group is Port Macquarie’s Trusted Car Dealership

    May 13, 2025

    How To Improve Your Credit Score

    May 1, 2025

    MyGroundBiz: Empowering FedEx Ground Businesses

    April 29, 2025
    Leave A Reply Cancel Reply

    Latest Posts

    Patrick Auto Group is Port Macquarie’s Trusted Car Dealership

    May 13, 202514 Views

    Need an Accident Replacement Vehicle? Here’s What You Should Know

    May 13, 20254 Views

    How To Improve Your Credit Score

    May 1, 20256 Views

    MyGroundBiz: Empowering FedEx Ground Businesses

    April 29, 20258 Views
    Stay In Touch
    • Facebook
    • Twitter
    • Pinterest
    • Instagram
    • YouTube
    • Vimeo
    Don't Miss

    Sierra Mist Lawsuit: The Reason Why PepsiCo Replaced it With Starry

    By EllianaMarch 20, 2025

    The Rise and Fall of Sierra Mist For years, Sierra Mist has been a beloved…

    Ekstensive Metal Works Lawsuit: Unraveling the Controversy

    March 19, 2025

    What is Int l digital charge on your bank statement?

    August 2, 2024

    Subscribe to Updates

    Get the latest creative news from SmartMag about art & design.

    About Us

    Welcome to Business Vibrant - Where Insight Meets Innovation. At Business Vibrant, we are dedicated to providing valuable insights, expert opinions, and innovative ideas in the ever-evolving world of business.

    Facebook X (Twitter) Pinterest YouTube WhatsApp
    Our Picks

    Patrick Auto Group is Port Macquarie’s Trusted Car Dealership

    May 13, 2025

    How To Improve Your Credit Score

    May 1, 2025

    MyGroundBiz: Empowering FedEx Ground Businesses

    April 29, 2025
    Most Popular

    Sierra Mist Lawsuit: The Reason Why PepsiCo Replaced it With Starry

    March 20, 2025655 Views

    Ekstensive Metal Works Lawsuit: Unraveling the Controversy

    March 19, 2025426 Views

    How to Find the Top Swimming Pool and Renovation Company?

    November 28, 202450 Views
    © 2025 businessvibrant.com
    • About Us
    • contact us
    • Privacy Policy
    • Terms of service

    Type above and press Enter to search. Press Esc to cancel.